CONSTRUCTION OF AN AMMONIA PLANT NEAR KINGISEPP. JSC "EUROCHEM NORTH-WEST". PHASE II

RTL Company successfully transported in November 2017 a startup boiler for the construction of ammonia enterprise in Kingisepp in Russia.

RTL Company successfully transported in November 2017 a startup boiler for the construction of ammonia enterprise in Kingisepp in Russia.

The cargo was delivered by road from the producer to the port of shipment in Taranto, Italy, where it was loaded on an ocean-going freighter and reliably fastened. Upon arrival in Ust-Luga seaport in Russia the cargo was unloaded by shipboard cranes. After customs clearance the frame was partially dismantled to decrease the cargo width for further transportation. Major preparation work was done to arrange the transportation.

The railway crossing at Luzhskaya station was partially dismantled, power transmission line and overhead wiring was switched off and dismantled, street light poles were pulled down, driving over bridges and underground culverts was inspected and designed, a flyover bridge was reconstructed, etc.

The final stage was delivery by road to the customer warehouse. The stage is distinguished by a combination of the abnormal cargo size (11.0 meters wide and over 8.1 meters high) and the delivery distance of over 75 kilometers.