Cemeq Minerals

RTL Ltd during the period from May to December 2013, was carried out delivery of equipment for the construction of a Nickel processing plant in Guatemala. Shipping of cargo carried from several plant s of Russia. (OOO «Uralmashplant» Ekaterinburg, JSC «ORMETO-YUUMZ» Orsk, PKF «Globus», Saratov, JSC «Hydraulics» Gryazy JSC «UralSpetsMash» Magnitogorsk), and Electrical equipment also from Europe (Vakoma GmbH Germany, CMD Engrenages et reducteurs France, Paul Vahle GmbH & Co.KG Germany).

 

Delivery of equipment from Russia carried through Rostov-on-Don port and after that on vessel «river-sea» type cargo delivered to Turkish port Izmir, where were loaded on ocean class vessel for shipment to the port of Santo Tomas de Castilla, Republic of Guatemala.

 

The total amount of cargoes sent from Russia is 1 945 tons and 5 768 FRT. In connection with the peculiarities of the technological process and output equipment of manufacture, it was decided to divide the total on two almost different lots. Dispatch first lot was done from such plants as LLC «Uralmashzavod», Ekaterinburg, JSC Machine-building concern ORMETO-YUMZ, Orsk and OOO PKF «Globus», city of Saratov.

From the Yekaterinburg plant was sent 18 sections with a diameter of almost 6 meters, which will subsequently become the underlying furnace for processing of Nickel ore.

From Orsk plant were sent parts for gear and semi bandages, which were delivered to JSC «shipbuilding yard «LOTOS», Astrakhan for welding semi bands in a single bandage, diameter 6.7 metres, weight 71 per ton, which were subsequently delivered to the port of Rostov-on-don on the riverboat.

After accumulation of the total party in the Rostov-on-don port, cargo was carried out loading and lashing on vessel «river-sea» type for transportation to transit port Turkey, Izmir, where was implemented overload on an ocean vessel and sent to a recipient in Guatemala.

The second lot was shipped from factories LLC «Uralmashzavod», Ekaterinburg, JSC Machine-building concern ORMETO-YUMZ, Orsk, JSC «hydraulic», Dirt, CJSC Uralspetsmash», Magnitogorsk. Also, as in the first lot from the factory LLC»Uralmashzavod» was sent 14 sections with a diameter about 6 meters, which were delivered to Rostov by truck. Also similar cargo was delivered from the factory JSC «Machine-building concern ORMETO-YUMZ» in Orsk partially right in Rostov and partly through JSC «shipbuilding yard «LOTOS» for welding of bandages.

The JSC «Hydraulic», Gryazi and ZAO «Uralspetsmash, Magnitogorsk shipped equipment, which also were delivered by truck to the port of Rostov-on-Don. After consolidation of whole party in the port was carried out shipping in Izmir and later in the port of Santo Tomas de Castilla, Guatemala.

The equipment that was sent from France and Germany totaled 313 tons and 512 FRT. European lot consolidated in the Belgian port of Antwerp. There was loaded in the ocean vessel for shipment to the port of the Republic of Guatemala.

In total, from Russia, France and Germany to the Republic of Guatemala was transported 2 258 tons, 6 280 FRT.